A Complete Garage, Driveway, and Deck Addition to a wonderful home in Bloomfield, NJ. Follow along with the complete journey of the project below.
9/12/23 - Pre-construction
A birds eye view of the project site where we will be creating a complete garage addition to this beautiful home in Bloomfield, NJ.
9/14/23 Demolition
Removal of the side ramp that is attached between the house and the driveway that must be removed before construction can begin.
9/17/23 - 9/22/23 - Excavation Rebar and Concrete Base Installation
Excavation of the site , installation of the rebar and the pouring of concrete for the foundation base.
10/2/23 - 10/4/23 - Concrete Block Base and Irrigation Installation
Concrete blocks, additional rebar, and irrigation canal excavation and installation.
10/10/23 - 10/11/23 - Site Preparation for Gravel and Concrete.
Preparation and leveling of site for gravel and concrete garage floor.
10/12/23 - 10/13/23 - Framing and Siding
Construction and framing of the garage, roofing and siding.
10/16/23 - 10/24/23 - Sheetrock, Decking, and Pavement Installation
Interior Sheetrock and Painting, Decking Materials, and Pavement Installation
11/3/23 - Driveway Sealer and Back Fencing Installation
Finishing the drive way with a coat of sealer, and a look at the addition of the new metal fencing surrounding the property.